Thanks for visiting the Haynes Project 50 Blog! Heres a summary of the Project 50 Team activities over the next two weeks:
1. Final assembly of the suspension and steering system to the car
2. Final assembly of the transmission
3. Beginning interior reassembly
Be sure to take a look at the Mustang Live Garage Camera to watch the restoration work live during business hours. Ask us any question or leave us a comment about the work. Till next time, the Haynes P50 Team
Read More..
1. Final assembly of the suspension and steering system to the car
2. Final assembly of the transmission
3. Beginning interior reassembly
Be sure to take a look at the Mustang Live Garage Camera to watch the restoration work live during business hours. Ask us any question or leave us a comment about the work. Till next time, the Haynes P50 Team